| Wiring
& Installation- PDU1 / APC Symmetra
Verify
that all incoming line voltage (utility power)
and low voltage (control) circuits are de-energized,
and locked out before installing cables or making
connections, weather in the junction box or to
the UPS unit.
Always
verify that all battery modules are removed and
all battery extension frames are disconnected
from the UPS unit before installing any wiring. |